Environmental Issues
Public registers
POEO Public Register
Licences, applications and notices search
Penalty notices search
Enforceable undertakings search
Enforceable undertakings media releases
Exemptions and approvals search
Prosecutions or civil proceedings search
Terms of use: POEO public register
Licensing FAQs
List of licences
Unlicensed premises regulated by the EPA
Contaminated land record of notices
About the record of notices
List of notified sites
Tips for searching
Disclaimer
Dangerous goods licences
Pesticide licences
Radiation licences
Home
Public registers
POEO Public Register
Licences, applications and notices search
Licence conditions for pollution studies and reduction program
Licence conditions for pollution studies and reduction programs
Summary
Licence number:
394
Title:
Supply Line Upgrade & Discharge Fault Response
Start date:
11 Jul 2013
Licence Condition
By 30 April 2014 the following works will be undertaken by the licensee at the premises: 1. Replacement of the Miller's dam supply line; 2. Installation of burst pipe protection on the Miller's dam supply line; 3. Replacement of the CHPP supply line; and 4. Installation of a system which ensures that the actuated outlet valve on the blended water pipe closes during power loss or failures of devicenet system.